FM · Professional Level
Investment Appraisal
Using discounted cash flow (DCF) techniques to evaluate investment projects. Net Present Value (NPV): relevant cash flows (incremental, cash-based, after tax), treatment of tax (capital allowances, timing of tax payments), inflation (money vs real cash flows, the Fisher formula), working capital investments (at start, recovery at end), perpetuities and growing perpetuities, annuities and annuity factors. Internal Rate of Return (IRR): calculation by interpolation, limitations (multiple IRRs, non-conventional cash flows, reinvestment assumption), Modified IRR (MIRR). Payback period (simple and discounted). Accounting Rate of Return (ARR). Profitability Index (PI). Equivalent annual cost/benefit (EAC/EAB) for projects with different lives. Capital rationing: single-period (PI ranking) and multi-period (linear programming). Risk and uncertainty: sensitivity analysis, scenario analysis, simulation, expected values with standard deviation, certainty equivalents. Real options (option to delay, expand, abandon, switch). Post-audit of investments.
Learning Objectives
- •Identify relevant cash flows for investment appraisal — incremental, cash-based, after tax
- •Calculate NPV including tax effects (capital allowances, timing), working capital, and inflation adjustments
- •Apply the Fisher formula to convert between real and money (nominal) cash flows and discount rates
- •Calculate IRR by linear interpolation and apply MIRR; recognise limitations of IRR
- •Apply the payback period, discounted payback, ARR, and profitability index
- •Calculate equivalent annual cost/benefit to compare projects with different lives
- •Apply capital rationing techniques for single-period (PI ranking) and introduce multi-period (LP) approaches
- •Incorporate risk and uncertainty using sensitivity analysis, scenario analysis, simulation, and expected values
- •Explain real options (delay, expand, abandon, switch) and their role in investment appraisal
Relevant Cash Flows
Investment appraisal uses cash flows, not profits, because cash is what is actually available for distribution or reinvestment. The key principles:
- Incremental: Only cash flows that CHANGE as a result of the project — existing cash flows continuing regardless are irrelevant
- Cash-based: Exclude non-cash items (depreciation, amortisation, profit/loss on disposal). Depreciation is NOT a cash flow — the relevant item is the purchase cost itself.
- After tax: Tax is a genuine cash outflow; project cash flows must be calculated post-tax. Include tax savings from capital allowances.
- Opportunity costs INCLUDED: The value that could be gained from the next-best alternative use of a resource (e.g., if land could be sold for £500k, using it on the project has an opportunity cost of £500k — even though no cash moves)
- Sunk costs EXCLUDED: Costs already incurred that cannot be reversed are not relevant (e.g., market research already paid for)
- Committed costs EXCLUDED: Costs already legally committed regardless of the project decision
- Financing costs EXCLUDED from the cash flows: Interest on borrowings is captured in the discount rate (WACC), NOT in the cash flows — otherwise it would be double-counted
Typical relevant cash flows:
| Time | Cash flow |
|---|---|
| t = 0 | Initial investment in PPE (purchase cost), Working capital investment |
| t = 1 to n | Sales revenue, Variable costs, Incremental fixed costs, Taxation (after capital allowances), Changes in working capital |
| t = n | Residual/scrap value of PPE, Recovery of working capital (net working capital released at project end), Any balancing allowance/charge on disposal |
Working capital:
- At the start: the project typically needs extra working capital (inventory, receivables less payables) — cash outflow at t=0
- During the project: if working capital requirement grows (e.g., as sales grow), additional investment each year — cash outflow
- At the end: working capital is "released" — cash inflow. Often assumed to be recovered at the end of the project's life.
- Only the INCREMENTAL change in working capital is a cash flow (not the total working capital balance)
Tax Adjustments in NPV
Corporation tax is a cash outflow that must be reflected in project cash flows. But tax is based on taxable profit, not cash flow. The main adjustments:
1. Tax on operating profits:
- Calculate the incremental taxable profit: Revenue − Variable costs − Fixed costs + Tax-deductible items − Depreciation add-back + Capital allowances
- Apply the corporation tax rate
- Deduct the tax in the cash flow statement at the appropriate time
2. Capital allowances (writing-down allowances):
- Although the purchase cost is a lump sum at t=0, the TAX SAVING comes via capital allowances claimed over the asset's life
- UK rule: typically 18% reducing balance (main rate pool) or 6% (special rate pool); Annual Investment Allowance (AIA) at 100% up to a threshold for most new plant and machinery; SBA (Structures and Buildings Allowance) at 3% SL for buildings
- For exam purposes, usually given a rate (e.g., 25% reducing balance)
- The tax SAVING = Capital allowance × Tax rate — this is a positive cash flow
- On disposal: a balancing charge (if disposal proceeds > tax WDV — extra tax) or balancing allowance (if disposal proceeds < tax WDV — extra tax saving) arises
3. Timing of tax cash flows:
- Two common conventions in exam questions:
- Tax paid in the same year as profits arise: tax shown at t=1, 2, 3… in the same year as the profit (simpler assumption)
- Tax paid one year in arrears: tax on year 1 profit paid at t=2 (more realistic for non-large companies; reflects 9 months after year-end payment deadline)
- The question will specify. Always read carefully.
Worked example of tax/capital allowance layout:
Suppose project: Initial investment £100k, life 4 years, residual value £10k, reducing balance capital allowances at 25%, tax 20%, tax paid same year:
| Year | Tax WDV opening | Capital allowance | Tax WDV closing | Tax saving (CA × 20%) |
|---|---|---|---|---|
| 1 | 100,000 | 25,000 | 75,000 | 5,000 |
| 2 | 75,000 | 18,750 | 56,250 | 3,750 |
| 3 | 56,250 | 14,063 | 42,188 | 2,813 |
| 4 | 42,188 | 32,188 (balancing) | 10,000 (= disposal) | 6,438 |
In year 4: balancing allowance = opening WDV £42,188 − disposal proceeds £10,000 = £32,188. Tax saving = £32,188 × 20% = £6,438.
Inflation — Money vs Real Cash Flows
When inflation is expected, the analysis must choose between:
- Money (nominal) terms: Cash flows inflated at expected inflation rates; discount using the MONEY (nominal) discount rate
- Real terms: Cash flows in today's prices (no inflation); discount using the REAL discount rate
CONSISTENCY RULE: Money cash flows must be discounted at the money rate; real cash flows must be discounted at the real rate. Mixing them will give the wrong answer.
The Fisher Formula:
| (1 + money rate) | = | (1 + real rate) × (1 + inflation rate) |
Rearranging: Real rate = (1 + money rate) / (1 + inflation rate) − 1
Example: Money rate 10%, inflation 4%. Real rate = 1.10 / 1.04 − 1 = 5.77%.
Or: Real rate 6%, inflation 3%. Money rate = 1.06 × 1.03 − 1 = 9.18%.
Different inflation rates for different items:
- If all cash flows inflate at the same rate, you can use EITHER the real approach (simpler — cash flows don't change) OR the money approach
- If cash flows inflate at DIFFERENT rates (e.g., revenue +4%, variable costs +5%, labour +6%), you MUST use the money approach because real cash flows would change over time
- Tax cash flows use the MONEY amounts (tax authority taxes nominal profits) — so when using the real approach, tax complications arise
- In practice, the money approach is safer when tax or differential inflation is involved
Typical exam scenario:
- Given: nominal cash flows (or information to inflate to nominal), nominal discount rate, inflation rate(s)
- Approach: use nominal throughout (discount nominal cash flows at nominal rate)
- If asked to show the real approach, deflate the cash flows (divide by (1+inflation)ⁿ) and discount at the real rate
NPV Variations — Perpetuities, Annuities, Equivalent Annual
Perpetuity (constant cash flow forever):
| PV of perpetuity | = | Annual cash flow / Discount rate |
Example: £10,000 per year forever at 8% = £10,000 / 0.08 = £125,000.
Growing perpetuity (constant growth rate g forever):
| PV of growing perpetuity | = | Next year's cash flow / (Discount rate − Growth rate) |
Example: Next year £10,000, growing 3% per year, discount 8%: £10,000 / (0.08 − 0.03) = £200,000.
Warning: formula breaks down if g ≥ r. Growth rate must be below discount rate for the formula to give a meaningful (finite) PV.
Annuity (constant cash flow for n years):
| PV of annuity | = | Annual cash flow × Annuity factor (AF) |
| Annuity factor | = | (1 − (1+r)⁻ⁿ) / r |
Example: £10,000 per year for 5 years at 8%. Annuity factor = (1 − 1.08⁻⁵) / 0.08 = 3.9927. PV = £10,000 × 3.9927 = £39,927.
Delayed annuity: For cash flows starting in year k+1 for n years: PV = (Annual CF × AF for n years) × (1+r)⁻ᵏ. Multiply the annuity by the single-period discount factor for the delay.
Equivalent Annual Cost (EAC) or Equivalent Annual Benefit (EAB):
Used to compare projects with different lives. Converts the PV of the project's total cash flows into an equivalent annual amount:
| EAC | = | Total PV of costs / Annuity factor (n years, at the cost of capital) |
| EAB | = | NPV (positive) / Annuity factor |
Example: Project A: 5-year machine, PV of all costs £30,000. Project B: 8-year machine, PV of all costs £40,000. Cost of capital 10%.
- Project A EAC: £30,000 / AF(5, 10%) = £30,000 / 3.7908 = £7,913 per year
- Project B EAC: £40,000 / AF(8, 10%) = £40,000 / 5.3349 = £7,498 per year
- Project B has a lower EAC — chosen (better value per year)
Alternative: compare NPV over the lowest common multiple of lives (5 and 8 → 40 years of chained replacements). EAC is much simpler and gives the same ranking.
Internal Rate of Return (IRR) and MIRR
The IRR is the discount rate at which NPV = 0. It represents the project's intrinsic rate of return. Accept projects where IRR > cost of capital; reject if IRR < cost of capital.
Calculating IRR by linear interpolation:
Calculate NPV at two discount rates (one giving positive NPV, one negative):
| IRR | = | a + [NPVa / (NPVa − NPVb)] × (b − a) |
Where a is the lower rate (gives positive NPV) and b is the higher rate (gives negative NPV).
Example: At 10%, NPV = £20,000. At 20%, NPV = −£5,000.
IRR ≈ 10% + [£20,000 / (£20,000 − (−£5,000))] × (20% − 10%) = 10% + (£20,000 / £25,000) × 10% = 10% + 8% = 18%.
Limitations of IRR:
- Multiple IRRs: Non-conventional cash flows (more than one sign change in cash flows — e.g., a project with a large clean-up cost at the end after positive cash flows) can produce multiple IRRs. NPV remains well-defined, IRR becomes ambiguous.
- Mutually exclusive projects: When choosing between mutually exclusive projects, IRR can give wrong rankings because it ignores SCALE. A smaller project with higher IRR may have lower NPV than a larger project with lower IRR.
- Reinvestment assumption: IRR implicitly assumes cash flows are reinvested at the IRR itself — often unrealistic, especially if IRR is very high.
- Single-number summary can be misleading for complex projects.
Modified IRR (MIRR): Addresses the reinvestment assumption. Assumes cash INFLOWS are reinvested at the cost of capital (rather than at the IRR) and OUTFLOWS are financed at the cost of capital. Gives a more realistic measure of the project's return.
| MIRR | = | [Terminal value of inflows / PV of outflows]1/n − 1 |
Where: Terminal value = sum of inflows compounded forward to year n at cost of capital; PV of outflows = sum of outflows discounted to year 0 at cost of capital.
NPV vs IRR — which should we use? NPV is theoretically superior — gives absolute value in £, consistent with shareholder wealth maximisation, always unique, handles non-conventional cash flows. IRR has intuitive appeal (a rate of return) and doesn't require knowing the discount rate in advance. Most finance professionals use NPV for final decisions but report IRR for communication.
Other Appraisal Methods
Payback period: The time required for cumulative cash inflows to equal the initial investment. "How long before we get our money back?"
- Simple payback: ignores time value of money — just cumulative undiscounted cash flows
- Discounted payback: uses discounted cash flows — always longer than simple payback
- Advantages: simple, intuitive, useful for liquidity-constrained businesses, emphasises early cash flows (risk focus)
- Disadvantages: ignores cash flows AFTER the payback period (a project could fail just after payback and the measure wouldn't capture it), subjective cut-off, simple payback ignores time value
Accounting Rate of Return (ARR): Average accounting profit / Average or initial investment. Uses PROFIT (not cash flow), including depreciation. Ignores time value.
- Formula: Average annual accounting profit / Average investment × 100%
- Where: Average investment = (Initial cost + Residual value) / 2
- Accept if ARR ≥ target rate
- Disadvantages: uses profit not cash flow; ignores time value; target is arbitrary; based on accounting conventions that vary
Profitability Index (PI): The ratio of NPV of future cash flows to initial investment.
- PI = PV of future cash inflows / Initial investment. Accept if PI > 1.
- Alternatively: PI = NPV / Initial investment — and then accept if PI > 0
- Use: Primarily for ranking projects under CAPITAL RATIONING (see below)
Comparison table of methods:
| Method | Uses cash flows? | Uses time value? | Summary |
|---|---|---|---|
| Payback (simple) | Yes | No | Quick liquidity check; misses post-payback flows |
| Discounted payback | Yes | Yes | Better than simple; still misses later flows |
| ARR | No (uses profit) | No | Accounting-based; target arbitrary |
| NPV | Yes | Yes | Theoretically best; absolute value; aligns with shareholder wealth |
| IRR | Yes | Yes | Rate of return; can be ambiguous (multiple IRRs); ignores scale |
| PI | Yes | Yes | Useful for ranking under capital rationing |
Capital Rationing
Capital rationing arises when the entity cannot invest in all positive-NPV projects — typically because of constraints on available capital (internal budget limits or external market constraints).
Hard rationing: Imposed by external capital markets (e.g., cannot raise more debt or equity — lenders have refused). Often contentious in theory (an efficient market would fund positive-NPV projects).
Soft rationing: Imposed by management — internal budget limits, desire to avoid excessive borrowing, limits on management time/attention, risk appetite. More common in practice.
Single-period capital rationing (only one period is constrained):
- Use the Profitability Index (PI): Rank projects by PI (NPV per £1 of initial investment, or PV of inflows per £1 of investment)
- Accept projects in descending order of PI until capital is exhausted
- If project is divisible (can do part of a project): take fractional shares of the marginal project
- If projects are indivisible (all-or-nothing): test combinations of projects (possibly forgoing the best-PI project if its size doesn't fit with other good projects)
- If projects are mutually exclusive: can only choose one from a set
Worked example: £100,000 available; four projects:
| Project | Initial investment | NPV | PI (NPV/Investment) | Rank |
|---|---|---|---|---|
| A | £40,000 | £20,000 | 0.50 | 2 |
| B | £30,000 | £18,000 | 0.60 | 1 |
| C | £50,000 | £15,000 | 0.30 | 4 |
| D | £40,000 | £16,000 | 0.40 | 3 |
With divisible projects: Take B (£30k, PI 0.60), then A (£40k, PI 0.50), then 75% of D (£30k of £40k, PI 0.40). Total NPV = £18k + £20k + 75% × £16k = £50k.
With indivisible projects: Try combinations — B+A = £70k; B+A+D would be £110k (over budget); B+D = £70k; A+D = £80k; B+A = £70k leaves £30k idle. Best might be B+D (£70k, NPV £34k) if we can't complete D and need NPV maximisation. Or A+D (£80k, NPV £36k). Test all feasible combinations.
Multi-period capital rationing (constraint on more than one period): Requires Linear Programming (LP):
- Objective: maximise total NPV
- Subject to: capital constraints in each period; x values between 0 and 1 (proportions)
- Solved using LP software (Excel Solver, specialised packages)
- At FM level: understand the LP formulation; not typically required to solve a full LP manually
Risk and Uncertainty
Risk vs uncertainty:
- Risk: Possible outcomes are known and probabilities can be assigned
- Uncertainty: Possible outcomes may not be fully known; probabilities cannot be assigned
In practice, the distinction is blurry; techniques overlap.
1. Sensitivity analysis: How much can each INPUT variable change before NPV becomes zero (the project becomes unacceptable)?
- Calculate the sensitivity percentage = NPV / PV of the variable's cash flows × 100%
- Low sensitivity = small change makes NPV zero → high risk variable; pay close attention
- High sensitivity = large change needed → more robust to this variable
Example: NPV = £50,000. PV of revenue cash flows = £500,000. Sensitivity to revenue = £50,000 / £500,000 = 10%. Revenue can fall by 10% before NPV hits zero. A 10% fall is significant risk if demand is volatile.
Advantages: identifies critical variables; intuitive. Disadvantages: only one variable at a time (ignores correlations); doesn't give probability of outcomes; ignores possible positive surprises.
2. Scenario analysis: Evaluate NPV under different sets of assumptions — typically best case, base case, worst case.
- All key variables change together in a consistent way
- Unlike sensitivity analysis, captures CORRELATIONS between variables
- Provides a range of possible NPVs — useful for decision-making
3. Simulation (Monte Carlo):
- Specify probability distributions for each uncertain variable
- Run thousands of simulations (computer-based) — each draws random values from the distributions and calculates NPV
- Build up a probability distribution of NPV outcomes
- Can see: expected NPV, standard deviation, probability of negative NPV, percentiles (5% worst case, etc.)
- Advantages: captures correlations, gives full distribution. Disadvantages: requires good input distribution data; computer-intensive; false precision risk.
4. Expected values (EV): Probability-weighted outcome.
- EV of NPV = Σ (probability × NPV in that scenario)
- Also can calculate standard deviation and coefficient of variation for risk measurement
- Limitation: based on a single estimate that may not match any actual outcome (average may be impossible, like rolling a 3.5 on a dice)
- Assumes decision-maker is risk-neutral
5. Certainty equivalents (CE): Convert risky cash flows to "certain" equivalents, then discount at the risk-free rate.
- CE = Risky cash flow × α (where 0 < α < 1 reflects risk aversion)
- The more risky the cash flow, the lower α (more discount for risk)
- Alternative to using a risk-adjusted discount rate
Risk-adjusted discount rate (RADR): Add a risk premium to the cost of capital for riskier projects. Simple and common in practice. But can distort the analysis because it assumes risk grows exponentially with time.
Real Options
Real options theory applies option-pricing concepts to managerial decisions. Recognises that investment projects often contain FLEXIBILITY — options to change course as information arrives. Traditional NPV under-estimates value by ignoring this flexibility.
Four main types of real option:
| Option | Definition | Example |
|---|---|---|
| Option to delay (timing option) | Right to wait and invest later when more information is available | Mining company with a known resource — wait until commodity prices rise before developing |
| Option to expand (growth option) | Right to invest additional capital to scale up if project is successful | Launching a pilot product, then expanding if successful. R&D that might lead to follow-on opportunities. |
| Option to abandon (exit option) | Right to walk away from a project if it underperforms, possibly recovering some residual value | Project with a clear scrap or sale value if discontinued. Contractual right to exit a contract. |
| Option to switch | Right to switch between inputs, outputs, or modes of operation | Flexible manufacturing plant that can produce different products. Fuel-switching power station (gas vs oil). |
Real option value and uncertainty: Counter-intuitively, HIGHER uncertainty often means HIGHER option value — because there is more upside to capture when things go well, combined with limited downside (you can abandon). This contrasts with traditional NPV where higher uncertainty typically reduces value (via higher discount rate).
Valuation methods:
- Black-Scholes model: The European-option pricing formula applied to real options. Inputs: current value of underlying asset, exercise price (investment cost), risk-free rate, time to expiry, volatility of underlying asset.
- Binomial trees: Simpler; models possible paths of the underlying variable over time. Particularly useful for American options (can be exercised any time) and real options with multiple decision points.
- Monte Carlo simulation: For complex options with multiple sources of uncertainty.
Practical implications for investment appraisal:
- Projects with flexibility may be VALUABLE even when traditional NPV is zero or negative
- Don't kill projects too quickly — consider option to delay or abandon
- "Stage-gate" investment processes formalise real option thinking: stages of investment with decision points
- R&D and exploration often have substantial real option value
- FM exam may ask for CONCEPTUAL understanding rather than numerical Black-Scholes calculation
Post-Audit of Investments
Post-audit (post-completion audit) is the review of an investment decision AFTER the project has been in operation for a period. Compares actual outcomes with those projected at the time of approval.
Benefits of post-audit:
- Accountability: Managers proposing projects know their forecasts will be scrutinised — reducing optimism bias
- Learning: Identifies systematic errors in forecasting (e.g., consistent over-estimation of demand) — improves future appraisals
- Action: Identifies whether the project should be continued, modified, or abandoned
- Management development: Post-audit discipline encourages rigorous analysis and disciplined implementation
Limitations:
- Costly and time-consuming
- Hindsight bias — outcomes may depend on factors outside the manager's control; unfair to penalise
- May discourage managers from proposing innovative/risky projects for fear of criticism
- Difficult to isolate the project's contribution from other business changes
- Outcome may not be the manager's fault — external factors (economy, competitor actions, regulation)
Best practices for effective post-audit:
- Focus on LEARNING, not blame
- Audit only SIGNIFICANT projects (materiality threshold)
- Timing: typically 6-12 months after completion (enough data; not too late)
- Separate what was controllable from uncontrollable factors
- Report findings formally; incorporate lessons into future appraisal guidance
Examiner Focus
Common Pitfall
Study Tip
Examiner Focus
Watch Out
Study Tip
Study Tip
Written Practice
Investment Appraisal: Applied Requirement
Prepare a focused written answer with clear workings and justified recommendations.
A client has asked for a concise exam-style written response for a client or senior manager on investment appraisal. Use the key rules, calculations, risks, and professional judgement from this topic to structure your answer.
Answer Prompts
- •Identify the issue and explain why it matters in the scenario.
- •Apply the relevant technical rule, calculation, or framework.
- •State the commercial, ethical, tax, reporting, or assurance implication.
- •Conclude with a clear recommendation or exam-ready judgement.
Marking Focus
- Application to facts rather than textbook recall
- Clear structure and answer-first communication
- Balanced judgement where there is uncertainty
- Commercially sensible conclusion
Key Definitions
NPV (Net Present Value)
Sum of discounted cash flows: Σ CFₜ / (1+r)ᵗ. Accept projects if NPV > 0 (create shareholder value). The theoretically correct method of investment appraisal.
Relevant cash flows
Incremental, cash-based, after-tax cash flows that change as a result of the project. EXCLUDE sunk costs, committed costs, depreciation (non-cash), financing costs (in discount rate). INCLUDE opportunity costs, tax effects, working capital changes.
Fisher formula
(1 + money rate) = (1 + real rate) × (1 + inflation rate). Used to convert between real and money discount rates. Consistency: money cash flows → money rate; real → real.
Working capital in NPV
Initial investment at t=0; additional injections as project grows; RECOVERY at project end (net working capital released). Only INCREMENTAL changes are cash flows.
Capital allowances
Tax deductions for capital expenditure — typically reducing-balance writing-down allowances. Tax saving = capital allowance × tax rate. Balancing allowance/charge on disposal.
Annuity factor
(1 − (1+r)⁻ⁿ) / r. Used to calculate the PV of a constant cash flow stream for n years. PV = annual cash flow × annuity factor.
Perpetuity formula
PV = Annual cash flow / r (for constant perpetuity). Growing perpetuity: PV = next year's cash flow / (r − g) where g < r.
IRR (Internal Rate of Return)
Discount rate at which NPV = 0. Calculated by interpolation between two rates. Accept if IRR > cost of capital. Limitations: multiple IRRs with non-conventional cash flows, scale ignored for mutually exclusive projects, reinvestment assumption.
MIRR (Modified IRR)
[Terminal value of inflows (at cost of capital) / PV of outflows]^(1/n) − 1. Addresses IRR's unrealistic reinvestment-at-IRR assumption by assuming reinvestment at the cost of capital.
Equivalent Annual Cost (EAC)
Total PV of costs / Annuity factor. Converts a project's total cost to an equivalent annual amount, enabling comparison of projects with DIFFERENT lives. Lower EAC is better.
Profitability Index (PI)
NPV / Initial investment (or PV of inflows / Initial investment). Used to rank projects under capital rationing — select in descending order of PI.
Sensitivity analysis
Technique measuring how much each input variable can change before NPV = 0. Sensitivity % = NPV / PV of variable's cash flows × 100%. Identifies critical variables.
Real options
Managerial flexibility in investment projects — options to delay, expand, abandon, or switch. Traditional NPV ignores this value. Often valuable when uncertainty is high.
Key Formulas
Worked Examples
Related Topics
Key Takeaways
- ✓NPV uses INCREMENTAL, CASH-BASED, AFTER-TAX cash flows discounted at the cost of capital. Accept if NPV > 0. EXCLUDE: sunk costs, committed costs, depreciation (non-cash), financing costs (in discount rate). INCLUDE: opportunity costs, tax effects, working capital changes.
- ✓Tax in NPV: tax on operating profits (in same year or one year arrears); capital allowances (typically 25% reducing balance) give tax savings = CA × tax rate. Balancing allowance/charge on disposal. Working capital: invest at start, recover at end.
- ✓Inflation: consistency rule — money cash flows → money discount rate, real cash flows → real rate. Fisher formula: (1 + money) = (1 + real) × (1 + inflation). Use money approach when different items inflate at different rates.
- ✓NPV shortcuts: Perpetuity = CF/r. Growing perpetuity = CF₁/(r−g) with g<r. Annuity factor = (1 − (1+r)⁻ⁿ)/r. Equivalent Annual Cost = Total PV / Annuity factor — compares projects with different lives.
- ✓IRR: discount rate where NPV=0, calculated by interpolation. Limitations: multiple IRRs with non-conventional cash flows, ignores scale (mutually exclusive projects), unrealistic reinvestment-at-IRR assumption. MIRR addresses reinvestment. Prefer NPV theoretically.
- ✓Other methods: payback (simple or discounted) — liquidity focus; ARR — uses profit not cash; profitability index = NPV/investment — used for ranking under capital rationing.
- ✓Capital rationing: single-period — rank by PI, take in descending order (divisible projects) or test combinations (indivisible). Multi-period — linear programming formulation (maximise total NPV subject to period capital constraints).
- ✓Risk techniques: sensitivity (% change in variable → NPV=0), scenario (best/base/worst), simulation (Monte Carlo — full distribution), expected values, certainty equivalents, risk-adjusted discount rates. Real options: delay, expand, abandon, switch — flexibility has value especially when uncertainty is high. Post-audit: accountability, learning, action.
Practice Questions
Question 1 of 8
Which of the following is NOT a relevant cash flow for NPV analysis?
Question 2 of 8
The Fisher formula states:
Question 3 of 8
A project has capital allowances of £25,000 in year 1. The tax rate is 20%. The cash flow effect in the NPV for year 1 is:
Question 4 of 8
A cash flow of £10,000 per year forever is received, starting in year 1. At a discount rate of 8%, its present value is:
Question 5 of 8
Which of the following is a significant LIMITATION of IRR?
Question 6 of 8
Project A: 4-year life, PV of costs £10,000. Project B: 6-year life, PV of costs £14,000. Cost of capital 10%. AF(4, 10%) = 3.170; AF(6, 10%) = 4.355. Using Equivalent Annual Cost:
Question 7 of 8
Under capital rationing with DIVISIBLE projects, rank projects by:
Question 8 of 8
A real option to ABANDON a project creates value by:
Source and Version
Syllabus: ICAEW ACA Professional Level 2026 · Reviewed: 2026-05-04